Bridge Removal - Humula

Transport for New South Wales (TfNSW) is removing the bridge over Carabost Creek, Humula as part of the NSW Government’s rail infrastructure program across the country rail network.

Works are being completed by TfNSW’s contractor, John Holland Rail (JHR). JHR operate and maintain the Country Regional Network across NSW under a ten-year contract with TfNSW.

 

Why is the work being competed?

The bridge over Carabost Creek will be removed to reduce the risk to the public and the environment.

When will work commence?

Works are currently scheduled to be completed between Monday 29 July and Friday 9 August 2019, subject to final approvals and weather conditions.

Site operations will run from 7:00am to 6:00pm each day.

How will I be affected?

You may hear construction noise during site operations and see some extra vehicle and heavy machinery movements in the area.

We endeavour to minimise disruptions to local traffic and business as best as feasibly possible.

Please contact our Community Relations team on 1300 661 390 or email crn.enquiry@jhg.com.au for further enquiries.

 